Implementing SAP ePP/DS in toolmaking to integrate funda- mentally different types of tool production into a single planning environment, including prioritization.
WAGO GmbH & Co. KG connects, measures, controls, and networks—and does so worldwide, with simple solutions and intelligent connections. Since 1951, WAGO* has been a trusted partner to industry, embracing the responsibility that comes with being a leading provider of electrical interconnection and automation technology as well as interface electronics.
By implementing SAP ePP/DS in its toolmaking operations, WAGO aimed to make planning and scheduling more efficient, transparent, and responsive to actual demand. Different types of business—ranging from new tool design and development to repairs and the planning of wear parts—all draw on the same capacity. The challenge was to represent these orders within a single planning environment and prioritize them according to their respective importance. Particularly during periods of high capacity utilization and when urgent requirements arose at short notice, WAGO needed to be able to respond quickly and effectively to changing circumstances.
The goal of the project was to integrate all toolmaking processes into SAP ePP/DS planning and establish consistent prioritization. To improve planning transparency, the CONSILIO Column Framework was implemented, enabling additional information to be displayed in virtually all ePP/DS transactions. Supporting heuristics were also developed to facilitate planning. In addition, demand forecasting was to be integrated into ePP/DS to enable comprehensive, demand-driven planning for toolmaking.
The implementation phase took approximately six months and initially focused on WAGO‘s main plant in Minden, Germany. Preparations were then made to roll out the solution to the company‘s other German plants, as well as its plants in Poland and Switzerland.



Unique: Three fundamentally different demand drivers

WAGO‘s toolmaking operations serve exclusively the company‘s own manufacturing plants. As a result, the types of orders vary significantly, yet they must be processed in parallel and coordinated within a shared planning environment.
Additional challenges
Ergänzend zum Standard wurden im Projekt eigene Entwicklungen umgesetzt.
In addition to the standard, custom developments were implemented as part of the project.
CONSILIO Column Framework: A standard CONSILIO product that makes it easy to display additional information in virtually all ePP/DS transactions. This significantly increases the amount of information available to planners directly within planning screens.
The project also included a custom heuristic for automatically prioritizing orders based on the project network hierarchy. This heuristic prioritizes the entire network according to the planner‘s specifications. Additional heuristics were developed to reduce lead times and support the scheduling and unscheduling of orders.
The initial focus was on the SAP GUI transactions. Subsequent implementation phases will also incorporate Fiori apps, including the Fiori planning board and the associated reporting transactions.
The next step is also expected to include the use of an optimizer, although this has not yet been implemented. The current configuration, which enables maintenance orders to be scheduled, is not compatible with the optimizer.