Language & Region
Hydro

HYDRO | SAP SCM APO Implementation

Creation of an integrated, flexible and expandable solution for scheduling and sequencing
with SAP APO

"We had already used finite planning in an external solution tailored to our needs", says Mr. Biegert, Production Manager at HYDRO, "but this did not meet our requirements in terms of functionality, integration with SAP and future-oriented orientation". Since HYDRO was in the process of implementing SAP ERP, the choice quickly fell on SAP APO. The task here was to adapt the planning and optimization to the special business needs of HYDRO.

50
Years of innovative solutions
100
Countries
1200
Satisfied customers
35000
Products

The Challenges

  • Multi-level consideration of job priorities in the optimization
  • All important information at a glance - the product overview as central tool
  • Full transparency of missing parts and critical path
  • Individual heuristics for extended planning functionality
  • Integration of consumption-controlled products in planning and optimization
  • Scheduling of external procurement using an individual logic
  • Support of the process split

In CONSILIO we found a competent and reliable partner whose consultants listened to us, recognized our company-specific requirements, demonstrated pragmatic solution approaches through their cross-industry expertise and implemented them in SAP in a very short time.

Thomas Besch, Managing DirectorHYDRO KG

The CONSILIO solution

The MRP based DS scenario of SAP SCM APO was used as the basis for the implementation. This scenario enables a first step into the world of SCM planning with little effort, in a short time and with minimal risk. HYDRO was already using demand planning in SAP ERP and wanted to refine the planning results taking into account capacity and material availability constraints. For this scenario, it is not necessary to transfer all master data to SAP SCM APO, the transaction data such as stocks, sales orders, planned orders, production orders, etc. is sufficient.

The planned orders generated in SAP ERP are optimized in SAP SCM APO using the available functions. Capacity restrictions, material availability and dependencies between orders are taken into account across all BOM levels. SCM APO thus creates a feasible production plan and transparency from the customer order to the purchased part. Exception messages for particularly critical situations reduce the workload of the detailed planners.

Initial Situation and Project Content

The starting point for the collaboration was HYDRO's requirement for an integrated, flexible and expandable solution for scheduling and sequencing. ‘We were already using finite planning in an external solution tailored to our needs,’ says Mr Biegert, Production Manager at HYDRO, ’but this did not meet our requirements in terms of functionality, integration with SAP and future orientation.’ As HYDRO was in the process of implementing SAP ERP, the choice quickly fell on SAP APO. The task here was to adapt the planning and optimisation to HYDRO's specific business needs. ‘With CONSILIO, we had a partner with many years of expertise and project experience in SAP implementations at our side,’ adds Mr. Haine, Head of IT at HYDRO. ‘Working together, we managed to fulfil all requirements and crack some tough nuts in the process.’

SAP SCM Solution

As a complete solution, SAP Supply Chain Management (SCM) covers the entire spectrum of supply chain management and enables cross-company collaboration with suppliers and customers. With functions for planning, collaboration and coordination of the supply chain on a single platform, SAP SCM enables companies to transform their traditional, rather linear supply chains into adaptable, significantly more flexible logistics networks.

From planning to production, inventory replenishment and logistics, SAP SCM supports all processes, always based on actual demand. To do this, it uses the Advanced Planner & Optimiser (APO), a component of the SAP SCM solution. APO's planning function enables precise, multi-level planning of requirements and capacities so that companies can create feasible production plans based on real availability data.

Project Details

Production line for Ground Support Equipment (GSE) - tripod lifters

The MRP based DS scenario from SAP SCM APO was used as the basis for the implementation. This scenario makes it possible to take a first step into the world of SCM planning with little effort, in a short time and with minimal risk. HYDRO was already using MRP in SAP ERP and wanted to refine the planning results, taking into account capacity and material availability restrictions. For this scenario, it is not necessary to transfer all master data to SAP SCM APO; the transaction data such as stocks, sales orders, planned orders, production orders, etc. are sufficient. 

The planned orders generated in SAP ERP are optimised in SAP SCM APO using the available functions. Capacity restrictions, material availability and dependencies between orders across all BOM levels are taken into account. SCM APO thus creates a feasible production plan and transparency from the sales order to the purchased part. Exception messages for particularly critical situations reduce the workload of the detailed planners.

As part of the implementation, solutions had to be created in SCM APO for the following important points for HYDRO. CONSILIO was able to draw on existing solution concepts from other implementation projects.

1. Multi-level consideration of order priorities in the optimisation process

HYDRO assigns different priorities to orders to ensure that critical production orders are not only kept in view by the planner but also during optimisation. As part of the optimisation process, delays are then assigned corresponding costs depending on the respective priority.

For the reliable and consistent consideration of order priorities, it is important on the one hand that the priorities are passed on across the entire order network and on the other hand that the allocation of prioritised accesses to the corresponding requirements is maintained. CONSILIO has developed a clever concept for this based on multi-level fixed pegging, which ensures that our prioritised orders are actually given priority.

2. All important information at a glance - the product overview as a central tool

The product overview in APO is the planner's tool of choice for a quick overview of the planning situation for a selection of products. All planning-relevant data and exception messages relating to quantity or deadline problems are displayed here.

But for HYDRO this was not enough. Further information, including reorder levels, additional purchasing and batch size parameters, have found their way into the product overview according to HYDRO's specifications. ‘The product view has thus become one of the central planning tools for us,’ says Mr Biegert.

3. Full transparency of missing parts and critical path

An overview of missing parts and therefore of potential risks in production is essential for monitoring material availability. Here too, HYDRO wanted more. ‘It's not just enough for us to see which components are not yet in stock and are therefore being procured externally or are in production,’ explains Mr Biegert, ’we also want to recognise the critical order that is relevant for the timely delivery of a customer order in the network.’

The solution for this consists of several parts and is fully embedded in the context view of the product view. The order context represents the complete network of receipts and requirements. To display the missing parts list, all stock elements can be filtered out here using an additional switch. 

The critical order is determined according to the HYDROlogic via the critical start date and is marked in the order context. Additional fields such as start date, difference between requirement and availability date, ATP category, comment field, etc. provide the planner with all the necessary information.

The critical resource is also entered in the context view. By definition, this is the resource for which the order has the longest delay. With these enhancements, the order context has become an important tool for HYDRO in the regular monitoring of material availability.

4. Customised heuristics for extended planning functionality

One of HYDRO's planning requirements is the interactive scheduling and defixing of orders. ‘The most convenient way for us is to do this in the product view,’ explains Mr Biegert. ‘CONSILIO has expanded the planning options for us accordingly.’

This was made possible by implementing customised heuristics that can be used both interactively, e.g. via additional buttons in the menu bar of the product view, and for the planning run in the background.

5. Integration of consumption-controlled products in planning and optimisation

When using the APO PP/DS optimiser, the focus is on demand or schedule-controlled products. However, HYDRO also produces consumption-controlled materials on bottleneck systems. To ensure that these products are also scheduled correctly in an integrated optimisation run, taking finite capacities into account, an adjustment was necessary.

Normally, during optimisation, receipt elements without a requirement date are scheduled at the end of the optimisation horizon. ‘To prevent this for consumption-controlled products, the consultants at CONSILIO came up with a creative solution,’ reports Mr Biegert.

6. Scheduling of external procurement using customised logic

Correct scheduling in external procurement is often a tricky issue, partly because determining the requirement dates for stock transfers and parts provided for subcontracting in ERP and APO follows a different logic. In ERP, scheduling is usually based on the planned delivery time, whereas in APO it is based on the transport duration.

‘In order to create clarity for us and to enable the use of our HYDRO logic for the individual determination of the planned delivery time,’ explains Mr Biegert, “CONSILIO has also used planned delivery times in APO for the determination of requirement dates”.

7. Support of the process split

A work centre often provides several individual capacities and can therefore be occupied by several processes at the same time. As part of an operation split, an operation can be distributed to several individual capacities in parallel, thereby reducing the processing time. HYDRO wanted to use this functionality in APO, but the standard does not yet offer the use of splits in APO. A corresponding extension in APO provides a remedy here. The set-up and processing times of an operation are reduced according to the specified split factor.

The result

CONSILIO was able to map the HYDRO's requirements in SAP SCM APO on time and within budget. ‘In CONSILIO we have found a competent and reliable partner whose consultants listened to us, recognised our company-specific requirements, used their cross-industry expertise to identify pragmatic solutions and implemented them in SAP in a very short time,’ confirms Thomas Besch, Managing Director, HYDRO Systems KG.

HYDRO SYSTEMS KG

HYDRO started out in 1965 as a small mechanical engineering company in Biberach, an idyllic village in the Black Forest. It was here that a small group of dedicated employees developed and built the first tripod jacks and wheel change jacks. For almost 50 years now, HYDRO has been developing and producing innovative solutions for the construction, maintenance and repair of civil and military aircraft. The product range comprises over 35,000 products.

The company's strength lies in the development of customised solutions. Over 1200 customers in more than 100 countries rely on the expertise of the market leader in the aviation industry for ground support equipment (GSE) and maintenance tooling.

The HYDRO Group now employs over 500 highly qualified employees in a worldwide network of subsidiaries and branches.