At the start of the project, the Neutrik Group used production planning PP in SAP S/4HANA for production planning and execution. SAP PP/DS was not used in a side-by-side scenario before the S/4HANA transformation.
To ensure that the requirements for modern production planning can be optimally implemented at various production sites, the potential benefits of extended planning with PP/DS came into focus with S/4HANA.
This is because both planners and management lacked efficient control tools to harmonise multi-stage production with the business objectives of cost-optimised capacity utilisation. Effective supply chain processes such as the precise planning of the delivery of purchased parts or cross-plant parts planning could not be carried out and monitored transparently. This is where CONSILIO's consulting and development expertise in the area of SAP PP/DS came into play.
In addition to the pre-defined requirements for the solution, other challenges arose during the project. One example of this is the planning and implementation of multiple machine operation so that one employee can look after up to four machines.
The optimisation of throughput times, for example through a targeted reduction in set-up times or the adjustment of batch sizes for optimised machine utilisation, were also required.
The primary objective of the project was to increase productivity and transparency in the production plants and to introduce standardised and future-proof planning processes throughout the company.
The functional objectives of the project were to improve the ability to act and the flexibility of all project employees involved in the planning process. Among other things, they included a significant improvement in planning and capacity optimisation at all relevant production levels as well as the optimisation of planning automation procedures and the associated relief of employees from their routine activities.
The Neutrik Group's corporate planning envisages a significant increase in sales volume by 2025, which requires the planning system to be future-proof. The material flow is to be planned as leanly as possible and a pulling production without excessive stocks at the individual production stages is to be achieved.