EagleBurgmann | S/4HANA-Conversion

Conversion of the current SAP ECC landscape to S/4HANA 1809

Implementation Highlights

  • Harmonization of the Eagle Burgmann ERP system landscape
  • Use of new functionalities in S/4HANA 1809 to improve production, delivery and group reporting
  • Best-of-breed solution for more business process efficiency - improved performance through new HANA technology
  • Feedback of in-house developments and use of S/4 standard functions to utilize future innovation potentials
Daumen Icon - CONSILIO GmbH
45000
Customers worldwide
60
Subsidiary companies
5600
Employees
820
Million Euros in sales

Starting point

Before the project began, EagleBurgmann locations worldwide used around 30 site-specific ERP systems. However, a company data model for digitalisation should be available in a standardised ERP system. The driver for the conversion was therefore a harmonisation of the EagleBurgmann system landscape. The goal was to build an SAP Digital Core, in this case the S/4HANA system, to which all countries would migrate in the long term.

The question of whether a rollout of the existing ECC system would be a better alternative was quickly dropped due to the advantages of S/4HANA and the new business models. The digital core, which will initially be used in Germany, Austria and China, is to be rolled out to the other locations as quickly as possible.

CONSILIO is a strategic partner for the conversion of the current SAP ECC landscape to S/4 HANA 1809 at EagleBurgmann.

David Reibnegger, Partner CONSILIO GmbH

Challenges

  • Provision of a company-wide S/4 digitisation platform for all producing units
  • Conversion to S/4 using a hybrid project approach with the best mix of brownfield and greenfield
  • Tight project schedule of ten months and thus limited optimisation options for existing processes and interfaces
  • Code adaptation and S/4 readiness checks including the necessary pre- and post-conversion activities
  • Ensuring the existing functionality of interfaces to SAP (non-S/4) and third-party systems
  • Ongoing functioning of existing MES systems and customer add-ons under S/4
  • Simultaneous introduction of SAP GTS

 

Overview of the timebox approach
Timebox approach: fixed duration, fixed budget, variable scope

Project objectives & realisation

Strategic project goal

Provision of a company-wide S/4 digitisation platform, a core system for all EagleBurgmann manufacturing units – integrated with Lean Cloud ERP for smaller sales and service companies.

  • Best-of-breed solution for maximum business process efficiency
  • Cutting-edge technology as a basis for continuous improvement
  • Central master data backbone system

Key driver: speed factor

It was clear from the outset that the implementation project had to be completed in ten months so as not to delay downstream activities such as rollout and digitisation.

  • Project implementation and go-live in 2019
  • Fastest roadmap for implementing the EagleBurgmann Digital Core

Quick wins and benefits for the departments

  • Identify the standardisation potential of S/4 to reinstate functionalities with customer-specific coding in the standard
  • Use the speed potential of S/4 by applying innovative functionalities and new KPI apps
  • Increase process efficiency and reduce delivery times and inventories by using current key figures from production and scheduling

Innovations

Development of a future-proof platform for digitisation and provision of new functionalities for accompanying projects.

  • Establishment of a digital core for processes and master data before rollout
  • Investment in innovations that can be used in later projects, such as Fiori UI and finite production planning
  • Creation of a basis for the use of new, innovative technologies in the field of RPA (robotics), machine learning and digital manufacturing

Project highlights

UI5 app masking

Development and introduction of a UI5 app to selectively display exception messages in the MRP run in a matter of seconds. The result: an 80% time reduction through the use of CDS view technology, as well as a reduction in administrative work and storage costs.

Production versions

Timely creation and execution of production versions before the conversion, reduction of administrative work through regular testing of the migration report.

MRP areas

Creation of a new process under S/4 and execution of MRP areas immediately before the conversion. Training of employees in subcontracting and warehouse disposition.

Variant configuration

During the conversion, an error occurred in the configuration characteristics; the variant configuration in the customer order and the production orders were not resolved. In close cooperation with SAP, missing coding was replaced, the error was corrected and the conversion was carried out promptly.

Lessons Learned

  • Preparatory measures should be tackled early on and numerous sandbox tests should be carried out.
  • Sufficient time and effort should be planned for the initial conversion.
  • Risk management with a clear risk and fallback plan for the go-live and cutover is recommended.
  • Testing as often as possible, ideally on a productive copy, enables important routine in the conversion.

EagleBurgmann Germany GmbH & Co. KG

  • Industry sector: Mechanical engineering
  • Product range: Industrial sealing technology such as mechanical seals, seal supply systems, carbon floating ring seals, packings and gaskets, magnetic couplings, products according to API 682 4th Edition, expansion joints, special products and comprehensive services
  • Web: www.eagleburgmann.com
  • Solution: SAP S/4HANA 1809 | SAP Cloud Plattform & SAP ME/MII
  • Implementation partner: CONSILIO GmbH